Home »
Shared ice plant work to begin in late April
The City of Kimberley reports that work on the new shared ice plant for the Kimberley Civic Centre and the Kimberley Curling Club will begin in late April after the current system shuts down for the season.
This project is an important investment in safety, reliability, and long‑term facility sustainability, replacing equipment that has exceeded its lifespan, the city stated on social media.
The contractor has provided a commissioning date of early September. Once the system is operational, city crews will require approximately two weeks to build the ice.
“We now anticipate opening the facilities on September 18,” the city said.
“We understand this later start will affect several user groups and appreciate the community’s patience as we complete this essential upgrade.”
Updates will be shared as the project progresses.
City of Kimberley photo
e-KNOW